Court Street Sidewalk Project Change Orders

West Baton Rouge Parish

Summary

Two change orders on the LA 76 multi-use path project sparked a heated debate about paying for work done before council approval. One was denied as overpriced; the other was approved because it corrected a design quantity error at contract unit prices.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Sep 10, 2026.

Impact analysis

💰Financial impact

Change Order 3 would have cost $4,000; Change Order 4 adds $72,021 to the project.

✅Who benefits

Pedestrians and residents along Court Street will get the completed multi-use path and sidewalk project.

⚠️Who could be affected

Taxpayers absorb the $72,021 quantity correction, and the contractor loses the disputed $4,000 payment.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for West Baton Rouge Parish

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.