Court Street Sidewalk Project Change Orders
West Baton Rouge Parish
Summary
Two change orders on the LA 76 multi-use path project sparked a heated debate about paying for work done before council approval. One was denied as overpriced; the other was approved because it corrected a design quantity error at contract unit prices.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Sep 10, 2026.
Impact analysis
Change Order 3 would have cost $4,000; Change Order 4 adds $72,021 to the project.
Pedestrians and residents along Court Street will get the completed multi-use path and sidewalk project.
Taxpayers absorb the $72,021 quantity correction, and the contractor loses the disputed $4,000 payment.