The parish's fuel system project came in $208,000 over the original $540,000 estimate because the scope grew — bigger 12,000-gallon tank, electrical work, lighting, and controls. The council accepted the higher cost to consolidate fueling at the back of the Public Works property.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Mar 26, 2026.
Impact analysis
About $208,000 more from the capital outlay fund than originally planned.