Summary
The concrete road rehab program is wrapping up with one extra panel replacement on Commercial Drive and a small cost increase of $8,020.
At a glance
- Total mentions
- 7
- Last 30 days
- 2
Discussed at 2 meetings in the last 60 days; most recently Oct 27, 2026.
Impact analysis
An additional $8,020, covered by the roughly $200,000 budgeted annually for panel change-outs.
Drivers on Commercial Drive and other rehabbed parish roads.
Developers and owners of private bridges, who face new design and permitting costs.
Mentions & discussions (7)
Parish Council - Oct 27, 2026
Day 2 of the budget hearing was set to cover roads funding, the five-year roads capital outlay, and drainage — the money that fixes streets and keeps water moving during storms. No outcome is recorded.
Parish Council - Oct 22, 2026
Road overlays and patching are done, striping is nearly finished. DOTD expects a January 2027 groundbreaking on the LA 415 project, though the intercoastal bridge completion slipped to mid-2028.
Parish Council - Jul 23, 2026
The parish proposed a potential option to state transportation officials for the Rosedale Road bridge and is waiting to hear whether it's feasible; the president will follow up next week.
Parish Council - Jul 9, 2026
Crews have been ditches-digging and pipe-replacing across the parish ahead of road overlays coming within the next month. The big news: the Intracoastal Canal Bridge completion slipped to mid-2028, but a traffic switch putting Baton Rouge-bound traffic on the new bridge should happen mid-2027.
Parish Council - Jun 11, 2026
The parish road repaving program is now under contract with M-Trak, LLC at $1.15 million — about half a million under budget. Expect paving work on parish roads soon.
Parish Council - Apr 9, 2026
The concrete road rehab program is wrapping up with one extra panel replacement on Commercial Drive and a small cost increase of $8,020.
Parish Council - Jan 22, 2026
Anyone building a bridge on a road that could become public — or on private subdivision roads — now has to meet state-grade design standards with engineer-stamped plans and load ratings. Private bridge owners stay fully responsible for maintenance.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for West Baton Rouge Parish
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.