School zone turn lane project
A resident again pressed for the long-delayed left-turn lane on the east side of the high school, where cane trucks back up traffic. The project has been stuck in DOTD funding limbo for 2.5 years, though a possible state funding pot may bypass the usual process.
Court Street sidewalk project cost overrun
A bid-quantity error on the pedestrian bridge abutments is costing taxpayers another $39,424. Council members are frustrated with repeated change orders and are pressing for better quality control before a much larger project comes up.
New bridge overnight closures coming
DOTD plans to close the new Mississippi River bridge for four to five nights for sign work — parish officials pushed back on the 5 a.m. reopen time because that's when LA 1 is busiest. Roughly six months out.