School zone turn lane project
A resident again pressed for the long-delayed left-turn lane on the east side of the high school, where cane trucks back up traffic. The project has been stuck in DOTD funding limbo for 2.5 years, though a possible state funding pot may bypass the usual process.
LA 1 / Intercoastal construction delays
A resident warned that evening traffic on LA 1 South near the Intracoastal has become dangerous because flaggers aren't timing with the Walmart light. Councilman Hotard said he contacted the sheriff and DOTD, who will issue recommendations on best practices for directing traffic.
Roads Program and 415 Connector Cost Relief
The parish may take in Phillips Lane as a parish road as part of the 415 connector corridor, and test pile driving starts before year's end — talk of a ribbon cutting has begun.
2026 Asphalt Roads Rehabilitation Project
The concrete road rehab program is wrapping up with one extra panel replacement on Commercial Drive and a small cost increase of $8,020.
Court Street sidewalk project cost overrun
A bid-quantity error on the pedestrian bridge abutments is costing taxpayers another $39,424. Council members are frustrated with repeated change orders and are pressing for better quality control before a much larger project comes up.
Emily Drive Turn Lane
The 98% design plans are with DOTD awaiting final approval — a project residents have been waiting on.
Court Street Sidewalk Project Change Orders
Two change orders on the LA 76 multi-use path project sparked a heated debate about paying for work done before council approval. One was denied as overpriced; the other was approved because it corrected a design quantity error at contract unit prices.
New bridge overnight closures coming
DOTD plans to close the new Mississippi River bridge for four to five nights for sign work — parish officials pushed back on the 5 a.m. reopen time because that's when LA 1 is busiest. Roughly six months out.
2026 Road Materials Bids and Upcoming Overlays
Public works reported the combined roads/drainage mowing crews are on pace for five or six cuts this year versus the usual four, the Emily Drive project hit 95% preliminary design, the Rosedale/Lobdale intersection awaits an H-number, and there's still no decision on the Rosedale Road bridge replacement.
Rosedale Road bridge replacement on hold
Parish President Manola said DOTD's plan to replace the Rosedale Road bridge is on hold until emergency services routing can be planned. He and other officials meet Monday to push for solutions that minimize disruption for residents.
Poydras Bayou bridge replacement delay
The Poydras Bayou/Rosedale Road bridge replacement slipped to September 16, and the 29-mile detour is still a safety concern. The Parish President is pressing state officials for a meeting on the detour route.
Lukeville Lane traffic signal fix
DOTD plans a June signal change at the Lukeville Lane/LA 1 light, giving green to one direction at a time; council is pressing for confirmation the fix was actually modeled before installation.
Acadian Trail project advancing
The Acadian Trail bike/pedestrian project, underway since 2016, reached substantially complete design; servitude agreements with property owners can now be signed so the project can go out for bid.
Drainage and roads maintenance update
Public Works reported culvert cleaning on Emile Drive, new speed signs on Fairview, and major canal clearing near the jail to improve drainage on LA 190. Sidewalk projects on Court Street and the Addis Acadian Trail are moving toward construction.
20 Percent Match for Regional Transportation Projects
The parish committed its local match for the Rosedale/Lobdale intersection and Emily Drive turn lane projects with the state and regional planning commission.
New bridge standards for public and private roads
Developers building bridges on future public roads now have to meet AASHTO engineering standards — stamped plans, load ratings, scour analysis, 20-foot width. Private subdivision bridges must be load-posted with documented maintenance plans, and the parish takes no liability for them.