2027 Employee Health Insurance Rates
The parish's switch to self-funded health insurance is paying off — only a 3% increase planned for 2027 while other governments like Baton Rouge are facing 20-30% hikes. The parish is building reserves to avoid big future spikes.
School zone turn lane project
A resident again pressed for the long-delayed left-turn lane on the east side of the high school, where cane trucks back up traffic. The project has been stuck in DOTD funding limbo for 2.5 years, though a possible state funding pot may bypass the usual process.
Flood insurance discounts maintained through CRS program
The annual Community Rating System report shows the parish keeps earning flood-insurance discounts for unincorporated residents through drainage work and repetitive-loss projects.
Arena Well No. 2 project wraps up cheaper
The parish's new water well at the arena is nearly done and came in about $99,360 under the original contract, partly because the well was drilled successfully on the first try. Total contract now about $2.9 million.
2026 Fire Department and General Fund Budget Amendments
The council introduced an ordinance amending the 2026 Fire Department and General Fund budgets. It comes back for a public hearing and vote on June 11, 2026.
LA 1 / Intercoastal construction delays
A resident warned that evening traffic on LA 1 South near the Intracoastal has become dangerous because flaggers aren't timing with the Walmart light. Councilman Hotard said he contacted the sheriff and DOTD, who will issue recommendations on best practices for directing traffic.
Regional Sewer Consolidation Project
The parish is exploring restricting general fund money to build a required reserve so sewer customers don't see a rate increase from the consolidated treatment plant project.
Drainage Fund and Flood Control Project
After 8+ inches of rain fell in about a day, parish drainage held up with no reported house flooding. Work on the Loup Lane culvert and a promising drainage study continue.
2027 Parish Budget — Day 1 Review
The parish is putting together its 2027 budget with a 5% cost-of-living salary bump, 3% insurance increases, and most operating expenses growing under the ~3.7% inflation rate. General fund spending goes from about $13 million to $13.4 million.
2027 Parish Budget — Recreation and Community Centers
Recreage is going from 4 to 4.5 mills (approved by the council), bringing in $3.4 million, and $1.19 million in capital projects is planned — mostly new playground structures at aging parks like Rome, plus backstops, batting cages, and a walk track extension.
2027 Parish Budget — Trust Funds and Capital Outlay
The Video Poker Trust, Lighting District Trust, and buildings-and-land capital plans were on the Day 2 agenda. These dedicated funds pay for lighting districts and parish facilities.
2026 Asphalt Roads Rehabilitation Project
The concrete road rehab program is wrapping up with one extra panel replacement on Commercial Drive and a small cost increase of $8,020.
Roads Program and 415 Connector Cost Relief
The parish may take in Phillips Lane as a parish road as part of the 415 connector corridor, and test pile driving starts before year's end — talk of a ribbon cutting has begun.
Jail rate negotiations with U.S. Marshals
The parish is working with a consulting firm to negotiate a ~21% higher daily housing rate with the U.S. Marshals Service — from about $52.50 to roughly $63.50 per inmate per day. The state rate, stuck at $29.39, can't be negotiated.
Courthouse third floor renovation study
The sheriff, DA and judges want to convert the courthouse's unused third floor into secure inmate holding with a direct elevator to courtrooms, plus storage and office space. An architecture firm is developing feasibility quotes; the Criminal Court fund could help pay for it.
Community Coffee to occupy 2070 Commercial Drive
After weeks of rumors that the old Cons warehouse would become an ICE facility, the parish president confirmed Community Coffee LLC will use it for coffee manufacturing, storage and distribution.
Library budget typo fix
The library's digital books budget was entered as $3,000 instead of $35,000 — a typo now corrected so the library can keep buying e-books and audiobooks.
Proposed EMS rate increase
Fire District 1 plans to ask the council in December or January for an ~8% bump in EMS billing rates — about $125,000 in new revenue. Officials stressed parish residents won't pay it; only insurance companies and non-residents would.
Adding four dispatchers at Central Communications
Central Communications is budgeted to add four dispatcher positions to reduce constant overtime at the 24/7 dispatch center. The fund is collecting its full three mills — with a ballot amendment underway that would do away with that millage, which officials flagged for residents to research.
Court Street sidewalk project cost overrun
A bid-quantity error on the pedestrian bridge abutments is costing taxpayers another $39,424. Council members are frustrated with repeated change orders and are pressing for better quality control before a much larger project comes up.
2026 Property Tax Millages and Rollbacks
The parish's tax base is certified at $859 million, up 2.5%, and the millage rate rises to 101.4 mils. Expect higher tax bills, though businesses pay roughly 82% of property taxes. Five of ten constitutional amendments on the November 3 ballot deal with property taxes.
EMS response saves cyclist on the levee
A Port Allen couple credited parish EMS with saving Randy Steil's life after a cycling crash on the levee — a paramedic reached him in three minutes. The story underscored the value of the parish's own ambulance service.